Material Requirements Planning
Also: MRP
Material Requirements Planning (MRP) is the process of exploding a production plan through the bill of materials to calculate what components to buy or make, in what quantity and by when.
MRP is deterministic arithmetic over master data. Given a schedule, a bill of materials and lead times, it tells you what to order. It has no opinion about whether any of those inputs are true.
This is why MRP output is so often distrusted. The logic is rarely wrong; the lead times, yields and bills feeding it are stale, so planners override the results, and the overrides become the real plan.
Depends on, and is depended on by
- Master Production ScheduleA Master Production Schedule (MPS) is the committed statement of what will be produced, in what quantity and when, that drives material and capacity planning.
- Bill of materialsA bill of materials (BOM) is the structured list of components and quantities required to build a finished product, used to drive material planning and cost.
- Lead time variabilityLead time variability is the spread in how long replenishment actually takes, as distinct from its average, and a primary driver of required buffer stock.
- Distribution Requirements PlanningDistribution Requirements Planning (DRP) is the time-phased calculation of what stock each warehouse needs and when, rolled up the network into replenishment orders on its source.
- Demand Driven MRPDemand Driven MRP (DDMRP) is a planning method that places strategic decoupling buffers in the supply chain and replenishes them from actual orders rather than from a forecast.
- Advanced Planning and SchedulingAdvanced Planning and Scheduling (APS) is software that plans and sequences production against finite capacity and material availability, rather than the unlimited capacity MRP assumes.