Advanced Planning and Scheduling
Also: APS
Advanced Planning and Scheduling (APS) is software that plans and sequences production against finite capacity and material availability, rather than the unlimited capacity MRP assumes.
MRP works out what material is needed and when, but treats every line and machine as able to absorb whatever load arrives. APS reads the same orders, BOMs and stock, adds routings, run rates, changeover times and shift patterns, and builds a sequence the plant can actually run. Its outputs are a feasible schedule by resource and promise dates that reflect real constraints rather than a lead time field.
An APS schedule is only as feasible as the routing data behind it. Run rates and changeover times in master data are often what the line achieved on its best day, so the optimised sequence slips on the first shift and planners rebuild it in a spreadsheet. The second trap is nervousness: re-optimising every hour reshuffles the floor, which is why a frozen window near the present matters more than a better algorithm.
Depends on, and is depended on by
- Material Requirements PlanningMaterial Requirements Planning (MRP) is the process of exploding a production plan through the bill of materials to calculate what components to buy or make, in what quantity and by when.
- Master Production ScheduleA Master Production Schedule (MPS) is the committed statement of what will be produced, in what quantity and when, that drives material and capacity planning.
- Capacity planningCapacity planning is the check that the labour, machines and storage needed by a production plan actually exist in the periods the plan assumes.
- Available to PromiseAvailable to Promise (ATP) is the uncommitted stock and planned production that can still be promised to a new customer order with a reliable date.
- Mathematical optimizationMathematical optimization is the use of a solver to find the best decision, such as lowest cost or highest service, that satisfies every stated constraint on capacity, stock and supply.