Advanced Planning and Scheduling

Also: APS

Advanced Planning and Scheduling (APS) is software that plans and sequences production against finite capacity and material availability, rather than the unlimited capacity MRP assumes.

MRP works out what material is needed and when, but treats every line and machine as able to absorb whatever load arrives. APS reads the same orders, BOMs and stock, adds routings, run rates, changeover times and shift patterns, and builds a sequence the plant can actually run. Its outputs are a feasible schedule by resource and promise dates that reflect real constraints rather than a lead time field.

An APS schedule is only as feasible as the routing data behind it. Run rates and changeover times in master data are often what the line achieved on its best day, so the optimised sequence slips on the first shift and planners rebuild it in a spreadsheet. The second trap is nervousness: re-optimising every hour reshuffles the floor, which is why a frozen window near the present matters more than a better algorithm.

Depends on, and is depended on by