Distribution Requirements Planning (DRP) is the time-phased calculation of what stock each warehouse needs and when, rolled up the network into replenishment orders on its source.

DRP applies MRP logic to the distribution network. Each location nets its forecast against stock on hand, quantities in transit and safety stock, offsets the shortfall by the transit lead time, and passes planned orders to the location that supplies it. Summed at the top of the network, those planned orders become the demand signal the plant or the supplier plans against.

It is only as honest as its lowest tier. Inflated local forecasts and buffers padded at each depot compound as they roll upward, which makes DRP a quiet source of the bullwhip effect inside a single company. It also says nothing about fairness: when supply is short, the netting alone does not decide which location goes without, so an explicit allocation rule has to.