Distribution Requirements Planning
Also: DRP
Distribution Requirements Planning (DRP) is the time-phased calculation of what stock each warehouse needs and when, rolled up the network into replenishment orders on its source.
DRP applies MRP logic to the distribution network. Each location nets its forecast against stock on hand, quantities in transit and safety stock, offsets the shortfall by the transit lead time, and passes planned orders to the location that supplies it. Summed at the top of the network, those planned orders become the demand signal the plant or the supplier plans against.
It is only as honest as its lowest tier. Inflated local forecasts and buffers padded at each depot compound as they roll upward, which makes DRP a quiet source of the bullwhip effect inside a single company. It also says nothing about fairness: when supply is short, the netting alone does not decide which location goes without, so an explicit allocation rule has to.
Depends on, and is depended on by
- Supply planningSupply planning is deciding how demand will be met across the network: what to make, buy and move, where and when, within capacity, lead time and inventory limits.
- Material Requirements PlanningMaterial Requirements Planning (MRP) is the process of exploding a production plan through the bill of materials to calculate what components to buy or make, in what quantity and by when.
- Safety stockSafety stock is inventory held deliberately above expected demand to absorb variability in demand and supply, and to protect a target service level.
- Bullwhip effectThe bullwhip effect is the amplification of demand variability as orders travel upstream, so small changes at the shelf become large swings at the factory.
- Multi-Echelon Inventory OptimizationMulti-Echelon Inventory Optimization (MEIO) is setting stock targets for every tier of a network together, so buffers sit where they protect service at the lowest total inventory.