Planning
Reorder point
Also: ROP
A reorder point (ROP) is the stock level that triggers replenishment, set to cover expected demand over the replenishment lead time plus safety stock.
The arithmetic is simple. Staleness is what breaks it: reorder points set once and never revisited keep firing against demand patterns and lead times that moved on months ago.
When lead times are volatile rather than merely long, a static reorder point will be wrong in both directions across a year. The variability matters more than the average.
Depends on, and is depended on by
- Safety stockSafety stock is inventory held deliberately above expected demand to absorb variability in demand and supply, and to protect a target service level.
- Lead time variabilityLead time variability is the spread in how long replenishment actually takes, as distinct from its average, and a primary driver of required buffer stock.
- Material Requirements PlanningMaterial Requirements Planning (MRP) is the process of exploding a production plan through the bill of materials to calculate what components to buy or make, in what quantity and by when.
- Economic Order QuantityEconomic Order Quantity (EOQ) is the order size that minimises the combined cost of placing orders and holding stock, assuming steady demand and fixed ordering and holding costs.